In short
  • Under AIA A201-2017, submittals are shop drawings, product data and samples. They are not contract documents, and work that needs one shouldn't start until it is approved.
  • Procore, Autodesk Build, Bluebeam and Oracle's Submittal Exchange all handle routing, review and the log well.
  • The gaps sit around the tool: building the register from the spec book, chasing subs for packages, tying lead times to the schedule and reporting across projects.
  • Procore and Autodesk both have submittals APIs, so those gaps can be closed without leaving the tool your team already uses.
  • A reviewer still approves every submittal. Software speeds up the paperwork, not the judgment.

Why submittals go late

The switchgear has a 40-week lead time. The submittal for it sat in a sub's inbox for three weeks, went to the architect with the wrong cut sheet, and came back "revise and resubmit." The release date slipped, and now the schedule has a problem nobody saw coming in March.

Almost every late submittal follows that pattern. The review itself takes days. The waiting around it takes weeks.

Submittal software fixes a lot of this. It doesn't fix all of it, and the part it misses is often where the time goes.

What the contract actually asks for

On projects using the AIA A201-2017 general conditions, section 3.12 covers submittals. It names three kinds:

  • Shop drawings: drawings, diagrams and schedules prepared for the work by the contractor, a sub or a supplier.
  • Product data: brochures, performance charts, instructions and similar information about materials and equipment.
  • Samples: physical examples that set the standard the work will be judged by.

A few rules in that section shape everything downstream. Submittals are not contract documents. Work that requires a submittal shouldn't be done until the architect has approved it. And approval doesn't relieve the contractor of deviations it didn't point out.

The project specifications add the details. Division 01, section 01 33 00 "Submittal Procedures" in CSI MasterFormat, usually sets the format, timing and review periods. The technical sections list what each trade must submit. ConsensusDocs contracts follow a similar logic: the contractor is responsible for the accuracy of its submittals, and starting before approval is at its own risk.

That is why the register matters so much. Every required submittal starts as a line buried in a spec section.

What submittal software handles well

The major tools are good at the middle of the process.

  • Procore Submittals: workflows with ball-in-court, automatic notifications, revisions, packages and a submittal log. Since March 2026, Procore's Submittal Builder with AI drafts submittals from selected spec sections for Enhanced and Premier accounts in the US.
  • Autodesk Build (renamed Autodesk Forma Build in 2026): submittal items, review steps, packages and spec sections. AutoSpecs reads the spec book and proposes a submittal register, flagging items that look missing.
  • Bluebeam: submittal workflows in Bluebeam Cloud, and markup in Studio that many reviewers already use.
  • Oracle Primavera Submittal Exchange: a cloud service for routing and stamping, used on many owner-driven and public projects.

If your firm runs one of these and the team actually uses it, keep it. Replacing a working submittal tool is rarely the answer. The question is what sits on either side of it.

Where the time still goes

Building the register

Someone reads 1,200 pages of specs and types every required submittal into the log. AI tools now help with this inside Procore and Autodesk, on the right plans. On other plans, or on projects with unusual specs, it is still days of a project engineer's time, and anything missed shows up months later as a surprise.

Getting packages from subs

The tool tracks who holds the ball. It can't make a sub send the right file. Packages arrive by email, half complete, with a cut sheet for the wrong model. Someone checks each one against the spec before it can go anywhere.

Lead times and the schedule

A submittal log knows the due date. It often doesn't know that the item behind it has a 30-week lead time and an install date in the schedule. Working backward from install to "submit by" is a spreadsheet exercise on most jobs, redone whenever the schedule moves.

Seeing across projects

Leadership wants to know which projects have overdue submittals, which architects take longest and which subs resubmit most. Each project's log answers its own piece. Putting them together is a monthly copy-and-paste job.

Closeout

O&M manuals, as-builts, attic stock and certificates are submittals too, usually listed in section 01 78 00. They pile up at the end of a job, when the team is already moving to the next one.

Where custom tools fit around it

Because Procore and Autodesk both publish submittals APIs, a firm can close these gaps without moving off the tool its team knows. A few examples of what that looks like:

  • A first-draft register: specs read section by section, required submittals proposed with the spec reference, and a project engineer approving the list before anything is created.
  • Package checks on arrival: a sub emails a package, and it is matched to the right submittal, checked for the items the spec asks for, and flagged if something is missing, before anyone opens it.
  • Lead-time tracking: each submittal tied to its procurement lead time and install date, so "submit by" dates move when the schedule does.
  • One view across projects: overdue items, review times by reviewer and resubmittal rates in one weekly report.

The APIs have limits worth knowing before anyone promises too much. Autodesk's documentation lists, for example, that its submittals API doesn't support batch imports or creating new item types and packages. Procore's API covers submittals, revisions, approvers, logs and packages. The design has to fit what each platform actually allows.

Questions to settle before you build anything

  • Which submittal tool is the record, and does every project use it the same way?
  • Which plan are you on? Some features, like Procore's AI submittal builder, depend on it.
  • Where do subs send packages today, and who checks them first?
  • Where do lead times live: the schedule, a procurement log, someone's spreadsheet?
  • Who approves what a tool proposes, and how is that recorded?

What most guides miss

The register is the whole game. A missed line in the register is a submittal nobody tracks until the material is needed. Time spent getting the register right at the start saves more than any workflow tweak later.

Approval doesn't move the risk. Under A201, an approved submittal doesn't excuse a deviation the contractor didn't flag. Any tool that pre-checks packages should make deviations easier to see, not easier to miss.

Subs are part of the system. A submittal process that only works for your own team still waits on everyone else. The easier it is for a sub to send the right thing the first time, the less chasing you do.

Keep the people who sign. Software can draft, match and remind. The architect, engineer and your project team still review and decide. Build it so their decision is recorded in the tool of record.

How we do it

We start with a free intro call and one project's submittal log. Then we work alongside your project team to build what's missing around Procore or Autodesk, through their supported APIs, with a person approving every submittal. See custom software for construction and our Procore and Autodesk Build pages for more.

Sources

  1. AIA Contract Documents: A201-2017 General Conditions (sample)
  2. AIA Contract Documents: What is a submittal in construction?
  3. CSI: MasterFormat numbers and titles
  4. ConsensusDocs: Shop drawings, the design's last mile
  5. Procore Support: Submittals release notes
  6. Procore Support: Best practices for submittal workflow management
  7. Procore Developers: Submittals API reference
  8. Autodesk Platform Services: ACC Submittals field guide
  9. Autodesk Construction Blog: Accelerate submittals with AutoSpecs
  10. Bluebeam: Submittal workflows
  11. Oracle: Primavera Submittal Exchange Cloud Service